Sequence- and time-dependent maintenance scheduling in twice re-entrant flow shops

Eghonghon Aye Eigbe*, Bart De Schutter, Mitra Nasri, Neil Yorke-Smith

*Corresponding author for this work

Research output: Contribution to journalArticleScientificpeer-review

19 Downloads (Pure)

Abstract

Industrial and academic interest converge on scheduling flow shops with sequence- and time-dependent maintenance. We posit that anticipatory, integrated scheduling of operational and maintenance tasks leads to superior performance to purely 'wait-then-fix' handling of the maintenance tasks. Motivated by an industrial problem with (sequence dependent) setup times, maximum separation constraints, and a combination of sequence- and time- dependent maintenance tasks, this paper introduces an integer programming solution, a constraint programming solution and a heuristic solution based on list scheduling. The motivating use case provides a unique combination of concerns that is to the best of our knowledge, not yet studied in the literature. We build on existing work where we can by extending models for sequence-dependent maintenance scheduling to accommodate sequence- and time-dependent maintenance scheduling and also propose other new models. We show the relative performances of our methods through empirical evaluations and also show significant improvements - up to 25% reduction in makespan - when compared to a reactive scheduling approach that does not consider maintenance in its planning. Based on our evaluations on exact methods, constraint programming models scale better than mixed integer programming models for this problem.

Original languageEnglish
Pages (from-to)103461-103475
Number of pages15
JournalIEEE Access
Volume11
DOIs
Publication statusPublished - 2023

Keywords

  • Flexible manufacturing systems
  • Integer programming
  • Job shop scheduling
  • Maintenance engineering
  • maintenance scheduling
  • makespan minimisation
  • Parallel machines
  • Production
  • re-entrant flow shops
  • Scheduling